Dept. of Trans. PROGRESS Serial No. Contract No. 12-082-13-25 03-3797U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 3% 03-SAC-80-M0.0/M10.4 Federal Project: ACIM-803(237) OTHR Progress payment No. 06 Payment period ending: 03-20-12 BAY CITIES / MYERS JV 3286 FITZGERALD ROAD RANCHO CORDOVA, CA 95742-6811 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,216,814.58 899,324.07 2.a. Extra Work 22,388.22 3,866.43 b. Adjustment Comp. 3. Materials on Hand 1,817,401.78 -15,530.41 4. Earned Subject to Retention 7,056,604.58 887,660.09 5. Mobilization 4,392,500.00 0.00 6. Total Work Completed 9,631,702.80 7. Deductions -20,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,429,104.58 882,660.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 882,660.09