Dept. of Trans. PROGRESS Serial No. Contract No. 12-142-13-05 03-3797U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 5% 03-SAC-80-M0.0/M10.4 Federal Project: ACIM-803(237) OTHR Progress payment No. 08 Payment period ending: 05-17-12 BAY CITIES / MYERS JV 3286 FITZGERALD ROAD RANCHO CORDOVA, CA 95742-6811 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,594,355.76 1,445,662.50 2.a. Extra Work 516,911.97 434,520.20 b. Adjustment Comp. 61,674.21 33,450.00 3. Materials on Hand 1,698,426.89 -174,545.26 4. Earned Subject to Retention 9,871,368.83 1,739,087.44 5. Mobilization 6,588,750.00 0.00 6. Total Work Completed 14,761,691.94 7. Deductions -11,000.00 17,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,449,118.83 1,756,087.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,756,087.44