Dept. of Trans. PROGRESS Serial No. Contract No. 12-205-10-48 03-3797U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 9% 03-SAC-80-M0.0/M10.4 Federal Project: ACIM-803(237) OTHR Progress payment No. 10 Payment period ending: 07-19-12 BAY CITIES / MYERS JV 3286 FITZGERALD ROAD RANCHO CORDOVA, CA 95742-6811 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,412,961.05 2,252,738.40 2.a. Extra Work 1,696,623.86 1,179,711.89 b. Adjustment Comp. 257,094.21 195,420.00 3. Materials on Hand 1,650,669.25 -70,487.00 4. Earned Subject to Retention 16,017,348.37 3,557,383.29 5. Mobilization 6,588,750.00 0.00 6. Total Work Completed 20,955,429.12 7. Deductions -6,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,600,098.37 3,557,383.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,557,383.29