Dept. of Trans. PROGRESS Serial No. Contract No. 13-169-08-41 03-3797U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 22% 03-SAC-80-M0.0/M10.4 Federal Project: ACIM-803(237) OTHR Progress payment No. 21 Payment period ending: 06-13-13 BAY CITIES / MYERS JV 3286 FITZGERALD ROAD RANCHO CORDOVA, CA 95742-6811 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,442,676.60 2,120,057.84 2.a. Extra Work 3,666,918.99 54,447.34 b. Adjustment Comp. 2,195,594.38 90,880.04 3. Materials on Hand 1,675,758.31 -184,517.25 4. Earned Subject to Retention 34,980,948.28 2,080,867.97 5. Mobilization 8,345,750.00 0.00 6. Total Work Completed 41,650,939.97 7. Deductions -30,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 43,296,698.28 2,080,867.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,080,867.97