Dept. of Trans. PROGRESS Serial No. Contract No. 14-056-13-47 03-3797U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 36% 03-SAC-80-M0.0/M10.4 Federal Project: ACIM-803(237) OTHR Progress payment No. 29 Payment period ending: 02-20-14 BAY CITIES / MYERS JV 3286 FITZGERALD ROAD RANCHO CORDOVA, CA 95742-6811 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,630,949.78 1,427,253.46 2.a. Extra Work 4,494,824.91 64,402.65 b. Adjustment Comp. 2,575,643.17 10,982.32 3. Materials on Hand 1,380,929.85 -12,990.97 4. Earned Subject to Retention 49,082,347.71 1,489,647.46 5. Mobilization 8,785,000.00 0.00 6. Total Work Completed 56,486,417.86 7. Deductions -21,422.40 41,868.50 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 57,845,925.31 1,531,515.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,531,515.96