Dept. of Trans. PROGRESS Serial No. Contract No. 14-083-09-44 03-3797U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 37% 03-SAC-80-M0.0/M10.4 Federal Project: ACIM-803(237) OTHR Progress payment No. 30 Payment period ending: 03-20-14 BAY CITIES / MYERS JV 3286 FITZGERALD ROAD RANCHO CORDOVA, CA 95742-6811 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,010,650.19 379,700.41 2.a. Extra Work 4,524,109.34 29,284.43 b. Adjustment Comp. 2,575,643.17 0.00 3. Materials on Hand 1,220,434.29 -160,495.56 4. Earned Subject to Retention 49,330,836.99 248,489.28 5. Mobilization 8,785,000.00 0.00 6. Total Work Completed 56,895,402.70 7. Deductions -21,422.40 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 58,094,414.59 248,489.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 248,489.28