Dept. of Trans. PROGRESS Serial No. Contract No. 14-147-10-44 03-3797U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 39% 03-SAC-80-M0.0/M10.4 Federal Project: ACIM-803(237) OTHR Progress payment No. 32 Payment period ending: 05-21-14 BAY CITIES / MYERS JV 3286 FITZGERALD ROAD RANCHO CORDOVA, CA 95742-6811 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,722,560.72 331,810.13 2.a. Extra Work 5,117,128.52 391,602.52 b. Adjustment Comp. 2,568,379.28 -8,940.26 3. Materials on Hand 1,246,869.12 -15,796.40 4. Earned Subject to Retention 50,654,937.64 698,675.99 5. Mobilization 8,785,000.00 0.00 6. Total Work Completed 58,193,068.52 7. Deductions -26,422.40 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 59,413,515.24 693,675.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 693,675.99