Dept. of Trans. PROGRESS Serial No. Contract No. 14-170-12-47 03-3797U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 41% 03-SAC-80-M0.0/M10.4 Federal Project: ACIM-803(237) OTHR Progress payment No. 33 Payment period ending: 06-16-14 BAY CITIES / MYERS JV 3286 FITZGERALD ROAD RANCHO CORDOVA, CA 95742-6811 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,030,881.20 308,320.48 2.a. Extra Work 5,117,128.52 0.00 b. Adjustment Comp. 2,568,379.28 0.00 3. Materials on Hand 1,225,198.55 -21,670.57 4. Earned Subject to Retention 50,941,587.55 286,649.91 5. Mobilization 8,785,000.00 0.00 6. Total Work Completed 58,501,389.00 7. Deductions -36,422.40 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 59,690,165.15 276,649.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 276,649.91