Dept. of Trans. PROGRESS Serial No. Contract No. 15-302-14-32 03-3797U4 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 68% Location: Federal Project: 03-SAC-80-M0.0/M10.4 ACIM-803(237) OTHR Progress payment No. 049 Payment period ending: 10-20-15 BAY CITIES / MYERS JV 3286 FITZGERALD ROAD RANCHO CORDOVA, CA 95742-6811 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 57,824,078.71 1,904,091.01 2. a. Extra Work 8,456,088.53 511,523.21 b. Adustment Comp. 2,696,898.33 0.00 3. Materials on Hand 1,333,433.00 64,650.00 4. Earned Subject to Retention 70,310,498.57 2,480,264.22 5. Mobilization 8,785,000.00 0.00 6. Total Work Completed 77,762,065.57 7. Deductions -95,385.40 -12,073.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 79,000,113.17 2,468,191.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,468,191.22