Dept. of Trans. PROGRESS Serial No. Contract No. 15-352-13-17 03-3797U4 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 64% Location: Federal Project: 03-SAC-80-M0.0/M10.4 ACIM-803(237) OTHR Progress payment No. 052 Payment period ending: 12-20-15 BAY CITIES / MYERS JV 3286 FITZGERALD ROAD RANCHO CORDOVA, CA 95742-6811 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 61,839,817.47 1,200,710.45 2. a. Extra Work 9,254,891.19 116,649.70 b. Adustment Comp. 3,778,921.68 15,895.83 3. Materials on Hand 921,555.00 -283,669.00 4. Earned Subject to Retention 75,795,185.34 1,049,586.98 5. Mobilization 8,785,000.00 0.00 6. Total Work Completed 83,658,630.34 7. Deductions -93,385.40 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 84,486,799.94 1,046,586.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,046,586.98