Dept. of Trans. PROGRESS Serial No. Contract No. 01-172-13-41 03-382904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 15% 03-YOL-80-8.9/R10.1 Federal Project: ACNH-080-2(336) I-080-2(336) Progress payment No. 03 Payment period ending: 06-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 580,236.89 351,796.88 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 31,863.00 31,863.00 4. Earned Subject to Retention 612,099.89 383,659.88 5. Mobilization 185,550.00 61,850.00 6. Total Work Completed 765,786.89 7. Deductions 8. a.Contract Retentions -61,209.99 -38,365.99 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 736,439.90 407,143.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 407,143.89