Dept. of Trans. PROGRESS Serial No. Contract No. 01-205-12-31 03-382904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 6% 03-YOL-80-8.9/R10.1 Federal Project: ACNH-080-2(336) I-080-2(336) Progress payment No. 04 Payment period ending: 07-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01661 Total Estimate This Estimate 1. Contract Itms Without Mobil. 740,181.86 159,944.97 2.a. Extra Work 45,329.00 45,329.00 b. Adjustment Comp. 3. Materials on Hand 92,510.33 60,647.33 4. Earned Subject to Retention 878,021.19 265,921.30 5. Mobilization 185,550.00 0.00 6. Total Work Completed 971,060.86 7. Deductions 8. a.Contract Retentions -87,802.12 -26,592.13 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 975,769.07 239,329.17 10. Reduction Amt to Escrow 11. Payment to Escrow 87,800.00 12. Net Pymt. this Estimate 239,329.17