Dept. of Trans. PROGRESS Serial No. Contract No. 02-357-12-44 03-382904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 55% 03-YOL-80-8.9/R10.1 Federal Project: ACNH-080-2(336) I-080-2(336) Progress payment No. 21 Payment period ending: 12-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01661 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,149,623.58 116,480.21 2.a. Extra Work 461,245.57 112,057.40 b. Adjustment Comp. 594,175.20 -6,865.72 3. Materials on Hand 107,086.15 0.00 4. Earned Subject to Retention 4,312,130.50 221,671.89 5. Mobilization 247,400.00 0.00 6. Total Work Completed 4,452,444.35 7. Deductions -331,227.31 -400.00 8. a.Contract Retentions -215,606.53 -11,083.60 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,012,696.66 210,188.29 10. Reduction Amt to Escrow 11. Payment to Escrow 215,600.00 12. Net Pymt. this Estimate 210,188.29