Dept. of Trans. PROGRESS Serial No. Contract No. 03-204-11-44 03-382904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 03-YOL-80-8.9/R10.1 Federal Project: ACNH-080-2(336) I-080-2(336) Progress payment No. 28 Payment period ending: 07-18-03 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01661 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,705,532.63 94,086.29 2.a. Extra Work 768,862.40 71,637.13 b. Adjustment Comp. 569,233.56 -47,556.62 3. Materials on Hand 4. Earned Subject to Retention 6,043,628.59 118,166.80 5. Mobilization 247,400.00 0.00 6. Total Work Completed 6,291,028.59 7. Deductions -40,341.70 -29,941.70 8. a.Contract Retentions -302,181.43 -5,908.34 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,948,505.46 82,316.76 10. Reduction Amt to Escrow 11. Payment to Escrow 300,000.00 12. Net Pymt. this Estimate 82,316.76