Dept. of Trans. PROGRESS Serial No. Contract No. 03-296-09-57 03-382904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 03-YOL-80-8.9/R10.1 Federal Project: ACNH-080-2(336) I-080-2(336) Progress payment No. 29 Payment period ending: 10-20-03 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01661 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,634,488.81 -71,043.82 2.a. Extra Work 785,238.11 16,375.71 b. Adjustment Comp. 605,959.73 36,726.17 3. Materials on Hand 4. Earned Subject to Retention 6,025,686.65 -17,941.94 5. Mobilization 247,400.00 0.00 6. Total Work Completed 6,273,086.65 7. Deductions -20,800.00 19,541.70 8. a.Contract Retentions -302,181.43 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,950,105.22 1,599.76 10. Reduction Amt to Escrow 11. Payment to Escrow 302,180.00 12. Net Pymt. this Estimate 1,599.76