Dept. of Trans. PROGRESS Serial No. Contract No. 08-267-16-06 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 19% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 07 Payment period ending: 09-19-08 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,608,369.92 9,843,511.64 2.a. Extra Work 109,044.93 42,645.05 b. Adjustment Comp. -52,200.00 -52,200.00 3. Materials on Hand 959,926.22 -38,512.80 4. Earned Subject to Retention 35,625,141.07 9,795,443.89 5. Mobilization 7,177,250.00 0.00 6. Total Work Completed 41,842,464.85 7. Deductions -40,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 42,762,391.07 9,785,443.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,785,443.89