Dept. of Trans. PROGRESS Serial No. Contract No. 08-298-10-03 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 22% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 08 Payment period ending: 10-20-08 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,404,513.15 5,796,143.23 2.a. Extra Work 125,245.99 16,201.06 b. Adjustment Comp. -52,200.00 0.00 3. Materials on Hand 650,896.36 -309,029.86 4. Earned Subject to Retention 41,128,455.50 5,503,314.43 5. Mobilization 7,555,000.00 377,750.00 6. Total Work Completed 48,032,559.14 7. Deductions -335,000.00 -295,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 48,348,455.50 5,586,064.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,586,064.43