Dept. of Trans. PROGRESS Serial No. Contract No. 08-329-15-50 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 63% 25% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 09 Payment period ending: 11-20-08 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,588,698.16 1,184,185.01 2.a. Extra Work 301,413.78 176,167.79 b. Adjustment Comp. -57,514.40 -5,314.40 3. Materials on Hand 619,521.63 -31,374.73 4. Earned Subject to Retention 42,452,119.17 1,323,663.67 5. Mobilization 7,555,000.00 0.00 6. Total Work Completed 49,387,597.54 7. Deductions -438,462.00 -103,462.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 49,568,657.17 1,220,201.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,220,201.67