Dept. of Trans. PROGRESS Serial No. Contract No. 09-022-14-35 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 27% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 11 Payment period ending: 01-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,924,333.88 649,664.24 2.a. Extra Work 427,115.20 77,564.98 b. Adjustment Comp. -57,514.40 0.00 3. Materials on Hand 509,772.44 -276,498.31 4. Earned Subject to Retention 43,803,707.12 450,730.91 5. Mobilization 7,555,000.00 0.00 6. Total Work Completed 50,848,934.68 7. Deductions -48,462.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 51,310,245.12 440,730.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 440,730.91