Dept. of Trans. PROGRESS Serial No. Contract No. 09-055-15-55 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 30% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 12 Payment period ending: 02-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,121,710.83 197,376.95 2.a. Extra Work 431,711.50 4,596.30 b. Adjustment Comp. -104,255.15 -46,740.75 3. Materials on Hand 818,937.00 309,164.56 4. Earned Subject to Retention 44,268,104.18 464,397.06 5. Mobilization 7,555,000.00 0.00 6. Total Work Completed 51,004,167.18 7. Deductions -54,462.00 -6,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 51,768,642.18 458,397.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 458,397.06