Dept. of Trans. PROGRESS Serial No. Contract No. 09-146-11-45 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 38% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 15 Payment period ending: 05-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 47,484,914.26 2,636,845.23 2.a. Extra Work 528,911.33 8,402.24 b. Adjustment Comp. -45.09 -2,384.39 3. Materials on Hand 879,756.00 120,365.00 4. Earned Subject to Retention 48,893,536.50 2,763,228.08 5. Mobilization 7,555,000.00 0.00 6. Total Work Completed 55,568,780.50 7. Deductions -110,193.82 -26,846.82 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 56,338,342.68 2,736,381.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,736,381.26