Dept. of Trans. PROGRESS Serial No. Contract No. 09-202-13-39 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 32% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 17 Payment period ending: 07-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 51,307,235.61 2,055,441.26 2.a. Extra Work 590,177.26 -1,111.60 b. Adjustment Comp. 97,819.87 -4,768.77 3. Materials on Hand 389,864.00 -262,091.00 4. Earned Subject to Retention 52,385,096.74 1,787,469.89 5. Mobilization 7,555,000.00 0.00 6. Total Work Completed 59,550,232.74 7. Deductions -100,894.28 13,331.82 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 59,839,202.46 1,800,801.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,800,801.71