Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 09-218-12-34 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 32% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 18 Payment period ending: 07-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 51,313,878.38 6,642.77 2.a. Extra Work 605,690.64 15,513.38 b. Adjustment Comp. 97,819.87 0.00 3. Materials on Hand 389,864.00 0.00 4. Earned Subject to Retention 52,407,252.89 22,156.15 5. Mobilization 7,555,000.00 0.00 6. Total Work Completed 59,572,388.89 7. Deductions -100,894.28 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 59,861,358.61 22,156.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 22,156.15