Dept. of Trans. PROGRESS Serial No. Contract No. 09-267-10-30 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 38% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 20 Payment period ending: 09-17-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 58,555,780.16 3,041,241.78 2.a. Extra Work 645,105.22 35,594.33 b. Adjustment Comp. -221,367.61 -319,187.48 3. Materials on Hand 228,102.00 -13,734.00 4. Earned Subject to Retention 59,207,619.77 2,743,914.63 5. Mobilization 7,555,000.00 0.00 6. Total Work Completed 66,534,517.77 7. Deductions -75,894.28 30,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 66,686,725.49 2,773,914.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,773,914.63