Dept. of Trans. PROGRESS Serial No. Contract No. 09-296-15-31 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 41% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 21 Payment period ending: 10-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 60,905,803.89 2,350,023.73 2.a. Extra Work 722,266.44 77,161.22 b. Adjustment Comp. -221,367.61 0.00 3. Materials on Hand 179,180.00 -48,922.00 4. Earned Subject to Retention 61,585,882.72 2,378,262.95 5. Mobilization 7,555,000.00 0.00 6. Total Work Completed 68,961,702.72 7. Deductions -75,894.28 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 69,064,988.44 2,378,262.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,378,262.95