Dept. of Trans. PROGRESS Serial No. Contract No. 10-026-07-18 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 48% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 24 Payment period ending: 01-20-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 64,223,257.74 525,784.23 2.a. Extra Work 1,154,298.45 79,234.92 b. Adjustment Comp. -229,867.61 0.00 3. Materials on Hand 95,407.00 -51,241.00 4. Earned Subject to Retention 65,243,095.58 553,778.15 5. Mobilization 7,555,000.00 0.00 6. Total Work Completed 72,702,688.58 7. Deductions -74,614.66 23,611.44 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 72,723,480.92 577,389.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 577,389.59