Dept. of Trans. PROGRESS Serial No. Contract No. 10-054-12-01 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 51% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 25 Payment period ending: 02-22-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 64,661,832.10 438,574.36 2.a. Extra Work 1,383,588.34 229,289.89 b. Adjustment Comp. -186,867.69 42,999.92 3. Materials on Hand 75,585.00 -19,822.00 4. Earned Subject to Retention 65,934,137.75 691,042.17 5. Mobilization 7,555,000.00 0.00 6. Total Work Completed 73,413,552.75 7. Deductions -24,614.66 50,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 73,464,523.09 741,042.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 741,042.17