Dept. of Trans. PROGRESS Serial No. Contract No. 10-357-10-59 03-3864U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 60% 03-SUT-70-0.2/8.3 Federal Project: ACNH-P070(94) Progress payment No. 35 Payment period ending: 12-20-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 69,357,322.91 119,618.30 2.a. Extra Work 2,668,526.02 394,491.74 b. Adjustment Comp. 363,588.76 -788.67 3. Materials on Hand 4. Earned Subject to Retention 72,389,437.69 513,321.37 5. Mobilization 7,555,000.00 0.00 6. Total Work Completed 79,944,437.69 7. Deductions -53,688.57 63,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 79,890,749.12 576,321.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 576,321.37