Dept. of Trans. PROGRESS Serial No. Contract No. 05-145-10-44 03-395904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 03-YOL-80-R11.3/R11.4 Federal Project: ACBH-080-3(229) Progress payment No. 21 Payment period ending: 05-20-05 AMERICAN CIVIL CONSTRUCTORS WEST COAST INC 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 02160 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,065,390.97 102,443.00 2.a. Extra Work 258,273.71 0.00 b. Adjustment Comp. 461,500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,785,164.68 102,443.00 5. Mobilization 515,000.00 0.00 6. Total Work Completed 6,300,164.68 7. Deductions -4,915.00 0.00 8. a.Contract Retentions -289,258.23 -5,122.15 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,005,991.45 97,320.85 10. Reduction Amt to Escrow 11. Payment to Escrow 289,250.00 12. Net Pymt. this Estimate 97,320.85