Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-049-15-50 03-3A0104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-5-15.6/22.8 Federal Project: ACIM-005-6(324) Progress payment No. 19 Payment period ending: 07-24-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,844,896.00 -158,295.00 2.a. Extra Work 6,583,460.84 88,520.84 b. Adjustment Comp. 163,987.38 2,460.00 3. Materials on Hand 4. Earned Subject to Retention 12,592,344.22 -67,314.16 5. Mobilization 1,133,000.00 0.00 6. Total Work Completed 13,725,344.22 7. Deductions -20,000.00 14,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,705,344.22 -53,314.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -53,314.16