Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 13-060-10-57 03-3A0424 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 33% 03-BUT-99-R32.4/R33.3 Federal Project: NONE Progress payment No. 21 Payment period ending: 02-20-13 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,267,759.75 0.00 2.a. Extra Work 230,156.56 103,400.55 b. Adjustment Comp. 216,008.64 2,000.00 3. Materials on Hand 280,739.41 0.00 4. Earned Subject to Retention 8,994,664.36 105,400.55 5. Mobilization 2,232,500.00 0.00 6. Total Work Completed 10,946,424.95 7. Deductions -11,590.75 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,215,573.61 105,400.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,400.55