Dept. of Trans. PROGRESS Serial No. Contract No. 13-168-14-19 03-3A0424 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 40% 03-BUT-99-R32.4/R33.3 Federal Project: NONE Progress payment No. 25 Payment period ending: 06-13-13 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,021,392.50 661,820.00 2.a. Extra Work 352,256.38 38,183.49 b. Adjustment Comp. 225,671.14 0.00 3. Materials on Hand 375,614.69 -28,469.02 4. Earned Subject to Retention 11,974,934.71 671,534.47 5. Mobilization 2,350,000.00 117,500.00 6. Total Work Completed 13,949,320.02 7. Deductions -8,590.75 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,316,343.96 789,034.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 789,034.47