Dept. of Trans. PROGRESS Serial No. Contract No. 02-052-10-22 03-3A21U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 43% 03-NEV-80-17.1/28.1 Federal Project: ACIM-080-4(169) ACIM-080-4(169) Progress payment No. 15 Payment period ending: 02-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01742 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,419,789.44 165,496.70 2.a. Extra Work 256,755.90 62,042.90 b. Adjustment Comp. -49,840.18 0.00 3. Materials on Hand 740,813.62 -37,544.88 4. Earned Subject to Retention 21,367,518.78 189,994.72 5. Mobilization 7,125,000.00 0.00 6. Total Work Completed 27,751,705.16 7. Deductions -42,333.00 -20,000.00 8. a.Contract Retentions -1,591,334.05 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 26,858,851.73 169,994.72 10. Reduction Amt to Escrow 11. Payment to Escrow 1,350,000.00 12. Net Pymt. this Estimate 169,994.72