Dept. of Trans. PROGRESS Serial No. Contract No. 02-113-12-39 03-3A21U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 43% 03-NEV-80-17.1/28.1 Federal Project: ACIM-080-4(169) ACIM-080-4(169) Progress payment No. 17 Payment period ending: 04-19-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01742 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,730,204.08 124,929.64 2.a. Extra Work 391,673.39 43,978.03 b. Adjustment Comp. -49,840.18 0.00 3. Materials on Hand 1,242,187.98 9,321.51 4. Earned Subject to Retention 22,314,225.27 178,229.18 5. Mobilization 7,125,000.00 0.00 6. Total Work Completed 28,197,037.29 7. Deductions -37,333.00 0.00 8. a.Contract Retentions -1,591,334.05 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,810,558.22 178,229.18 10. Reduction Amt to Escrow 11. Payment to Escrow 1,591,330.00 12. Net Pymt. this Estimate 178,229.18