Dept. of Trans. PROGRESS Serial No. Contract No. 02-142-14-23 03-3A21U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 34% 03-NEV-80-17.1/28.1 Federal Project: ACIM-080-4(169) ACIM-080-4(169) Progress payment No. 19 Payment period ending: 05-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01742 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,097,843.35 1,353,639.27 2.a. Extra Work 634,925.57 192,592.13 b. Adjustment Comp. -29,695.04 15,500.00 3. Materials on Hand 1,249,581.23 -60,031.92 4. Earned Subject to Retention 23,952,655.11 1,501,699.48 5. Mobilization 7,125,000.00 0.00 6. Total Work Completed 29,828,073.88 7. Deductions -37,333.00 0.00 8. a.Contract Retentions -1,591,334.05 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 29,448,988.06 1,501,699.48 10. Reduction Amt to Escrow 11. Payment to Escrow 1,591,330.00 12. Net Pymt. this Estimate 1,501,699.48