Dept. of Trans. PROGRESS Serial No. Contract No. 03-204-06-31 03-3A21U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 80% 03-NEV-80-17.1/28.1 Federal Project: ACIM-080-4(169) ACIM-080-4(169) Progress payment No. 42 Payment period ending: 07-18-03 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01742 Total Estimate This Estimate 1. Contract Itms Without Mobil. 58,026,800.68 4,843,629.14 2.a. Extra Work 10,325,799.47 711,825.57 b. Adjustment Comp. 892,739.49 -1,206,258.50 3. Materials on Hand 1,211,222.88 54,943.27 4. Earned Subject to Retention 70,456,562.52 4,404,139.48 5. Mobilization 7,500,000.00 0.00 6. Total Work Completed 76,745,339.64 7. Deductions -86,633.00 0.00 8. a.Contract Retentions -3,522,828.13 -220,206.98 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 74,347,101.39 4,183,932.50 10. Reduction Amt to Escrow 11. Payment to Escrow 3,522,820.00 12. Net Pymt. this Estimate 4,183,932.50