Dept. of Trans. PROGRESS Serial No. Contract No. 04-146-11-22 03-3A21U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 91% 03-NEV-80-17.1/28.1 Federal Project: ACIM-080-4(169) ACIM-080-4(169) Progress payment No. 59 Payment period ending: 05-20-04 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01742 Total Estimate This Estimate 1. Contract Itms Without Mobil. 75,965,992.45 563,245.75 2.a. Extra Work 11,983,004.68 93,637.77 b. Adjustment Comp. 2,389,141.12 0.00 3. Materials on Hand 79,116.90 0.00 4. Earned Subject to Retention 90,417,255.15 656,883.52 5. Mobilization 7,500,000.00 0.00 6. Total Work Completed 97,838,138.25 7. Deductions -162,753.54 20,000.00 8. a.Contract Retentions -4,520,862.76 -32,844.18 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 93,233,638.85 644,039.34 10. Reduction Amt to Escrow 11. Payment to Escrow 4,500,000.00 12. Net Pymt. this Estimate 644,039.34