Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 04-212-12-42 03-3A21U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 96% 03-NEV-80-17.1/28.1 Federal Project: ACIM-080-4(169) ACIM-080-4(169) Progress payment No. 63 Payment period ending: 07-20-04 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01742 Total Estimate This Estimate 1. Contract Itms Without Mobil. 78,150,796.34 199,820.81 2.a. Extra Work 12,271,703.09 4,562.14 b. Adjustment Comp. 2,403,902.67 0.00 3. Materials on Hand 4. Earned Subject to Retention 92,826,402.10 204,382.95 5. Mobilization 7,500,000.00 0.00 6. Total Work Completed 100,326,402.10 7. Deductions -182,753.54 0.00 8. a.Contract Retentions -4,641,320.11 -10,219.15 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 95,502,328.45 194,163.80 10. Reduction Amt to Escrow 11. Payment to Escrow 4,500,000.00 12. Net Pymt. this Estimate 194,163.80