Dept. of Trans. PROGRESS Serial No. Contract No. 09-202-18-15 03-3A2204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 23% 03-NEV-80-28.1/31.8 Federal Project: ACBI-GV08(1) M-GV08(1) Progress payment No. 05 Payment period ending: 07-20-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,352,032.10 2,260,116.99 2.a. Extra Work 88,644.59 77,394.59 b. Adjustment Comp. 350,994.44 -13,069.33 3. Materials on Hand 73,724.88 -35,282.04 4. Earned Subject to Retention 6,865,396.01 2,289,160.21 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 9,791,671.13 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,865,396.01 2,289,160.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,289,160.21