Dept. of Trans. PROGRESS Serial No. Contract No. 10-053-10-58 03-3A2204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 50% 03-NEV-80-28.1/31.8 Federal Project: ACBI-GV08(1) M-GV08(1) Progress payment No. 12 Payment period ending: 02-22-10 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,446,166.70 3,300.00 2.a. Extra Work 280,775.70 58,615.82 b. Adjustment Comp. 299,526.06 0.00 3. Materials on Hand 926,528.51 -6,278.89 4. Earned Subject to Retention 19,952,996.97 55,636.93 5. Mobilization 3,800,000.00 0.00 6. Total Work Completed 22,826,468.46 7. Deductions -34,287.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,718,709.97 55,636.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 55,636.93