Dept. of Trans. PROGRESS Serial No. Contract No. 05-207-13-18 03-3A2604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 28% 03-NEV-49-7.3/8.1 Federal Project: ACST-P049(135) PH-P049(135) Progress payment No. 02 Payment period ending: 07-20-05 STIMPEL WIEBELHAUS ASSOCIATES P O BOX 492335 REDDING CA 960492335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 228,921.90 215,649.30 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 228,921.90 215,649.30 5. Mobilization 126,852.75 126,852.75 6. Total Work Completed 355,774.65 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 355,774.65 342,502.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 342,502.05