Dept. of Trans. PROGRESS Serial No. Contract No. 06-169-12-51 03-3C0604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 5% 13% 03-YUB-5503 Federal Project: NONE Progress payment No. 01 Payment period ending: 06-16-06 ALLEN L BENDER INC 2798 INDUSTRIAL BLVD WEST SACRAMENTO CA 95691 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 178,275.12 178,275.12 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 178,275.12 178,275.12 5. Mobilization 6. Total Work Completed 178,275.12 7. Deductions -4,000.00 -4,000.00 8. a.Contract Retentions -17,827.51 -17,827.51 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 156,447.61 156,447.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 156,447.61