Dept. of Trans. PROGRESS Serial No. Contract No. 05-237-17-57 03-3C1504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 100% 03-BUT-70-41.1/48.1 Federal Project: NONE Progress payment No. 03 Payment period ending: 08-19-05 GRAHAM CONTRACTORS INC P O BOX 26770 SAN JOSE CA 95159 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 419,617.42 40,572.50 2.a. Extra Work 33,322.41 33,322.41 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 452,939.83 73,894.91 5. Mobilization 6. Total Work Completed 452,939.83 7. Deductions -13,150.00 -3,150.00 8. a.Contract Retentions -22,646.99 -3,694.74 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 417,142.84 67,050.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,050.17