Dept. of Trans. PROGRESS Serial No. Contract No. 09-146-08-30 03-3E0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 20% 03-PLA-80-33.3/44.8 Federal Project: ACBI-GV08(2) M-GV08(2) Progress payment No. 03 Payment period ending: 05-20-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,693,167.48 5,407,203.47 2.a. Extra Work 48,683.29 41,218.93 b. Adjustment Comp. -23,836.50 -23,836.50 3. Materials on Hand 0.00 -248,056.50 4. Earned Subject to Retention 7,718,014.27 5,176,529.40 5. Mobilization 3,300,000.00 1,100,000.00 6. Total Work Completed 11,018,014.27 7. Deductions -9,866.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,008,148.27 6,276,529.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,276,529.40