Dept. of Trans. PROGRESS Serial No. Contract No. 09-169-15-26 03-3E0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 34% 03-PLA-80-33.3/44.8 Federal Project: ACBI-GV08(2) M-GV08(2) Progress payment No. 04 Payment period ending: 06-19-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,551,968.03 5,858,800.55 2.a. Extra Work 158,333.92 109,650.63 b. Adjustment Comp. -559,429.49 -535,592.99 3. Materials on Hand 4. Earned Subject to Retention 13,150,872.46 5,432,858.19 5. Mobilization 4,180,000.00 880,000.00 6. Total Work Completed 17,330,872.46 7. Deductions -9,866.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,321,006.46 6,312,858.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,312,858.19