Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-344-10-25 03-3E0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-80-33.3/44.8 Federal Project: ACBI-GV08(2) M-GV08(2) Progress payment No. 09 Payment period ending: 11-13-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,435,369.70 8,554.52 2.a. Extra Work 837,838.21 147,161.38 b. Adjustment Comp. -416,204.85 408,300.63 3. Materials on Hand 4. Earned Subject to Retention 40,857,003.06 564,016.53 5. Mobilization 4,400,000.00 0.00 6. Total Work Completed 45,257,003.06 7. Deductions -35,866.00 -13,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 45,221,137.06 551,016.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 551,016.53