Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-194-12-51 03-3E0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-80-33.3/44.8 Federal Project: ACBI-GV08(2) M-GV08(2) Progress payment No. 13 Payment period ending: 11-13-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,469,830.45 7,384.50 2.a. Extra Work 1,851,982.40 40,438.71 b. Adjustment Comp. -323,638.33 0.00 3. Materials on Hand 4. Earned Subject to Retention 41,998,174.52 47,823.21 5. Mobilization 4,400,000.00 0.00 6. Total Work Completed 46,398,174.52 7. Deductions -8,866.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 46,389,308.52 57,823.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,823.21