Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-294-11-21 03-3E0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-80-33.3/44.8 Federal Project: ACBI-GV08(2) M-GV08(2) Progress payment No. 15 Payment period ending: 11-13-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,469,830.45 0.00 2.a. Extra Work 1,872,238.00 15,249.82 b. Adjustment Comp. -323,638.33 0.00 3. Materials on Hand 4. Earned Subject to Retention 42,018,430.12 15,249.82 5. Mobilization 4,400,000.00 0.00 6. Total Work Completed 46,418,430.12 7. Deductions -8,866.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 46,409,564.12 15,249.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,249.82