Dept. of Trans. PROGRESS Serial No. Contract No. 15-146-12-49 03-3E1004 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 56% Location: Federal Project: 03-PLA-80-8.1/37.8 BHIM-803(243) Progress payment No. 013 Payment period ending: 05-20-15 RGW CONSTRUCTION INC 550 GREENVILLE ROAD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,539,084.43 1,907,019.03 2. a. Extra Work 323,592.02 34,232.71 b. Adustment Comp. 450,000.00 125,000.00 3. Materials on Hand 25,128.15 25,128.15 4. Earned Subject to Retention 7,337,804.60 2,091,379.89 5. Mobilization 1,636,850.00 0.00 6. Total Work Completed 8,949,526.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,974,654.60 2,091,379.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,091,379.89