Dept. of Trans. PROGRESS Serial No. Contract No. 16-113-09-24 03-3E1004 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 77% Location: Federal Project: 03-PLA-80-8.1/37.8 BHIM-803(243) Progress payment No. 024 Payment period ending: 04-20-16 RGW CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,823,110.54 610,734.25 2. a. Extra Work 2,000,277.11 708,906.52 b. Adustment Comp. 1,615,286.15 -4,002.00 3. Materials on Hand 4. Earned Subject to Retention 16,438,673.80 1,315,638.77 5. Mobilization 1,723,000.00 0.00 6. Total Work Completed 18,161,673.80 7. Deductions -367,903.82 -349,903.82 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,793,769.98 965,734.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 965,734.95